P95-B gas-fired power plant eyed in Quezon province
P95-B gas-fired power plant eyed in Quezon provinceds_30 / pixabay

Construction

Quezon Power proposes P95-billion Mauban gas plant and LNG terminal

QPL’s P95 billion, 1,230-MW gas plant and LNG terminal in Mauban would target a 2031 start and connect via 31 kilometres of new transmission line in Quezon.

Author
By Amara Osei
Filed
Length
3 min read

Key takeaways

  • QPL proposes a P95 billion, 1,230-MW gas-fired plant in Mauban.
  • Commercial operations are scheduled for the first quarter of 2031.
  • The 18.55-hectare site would include LNG storage, regasification and a jetty.
  • A 31-kilometer line would connect the plant to the 230-kilovolt Luzon network.
  • The DoE auction seeks 3,840 MW nationally and 2,900 MW for Luzon from 2026 to 2031.

By Amara Osei

Quezon Power (Philippines), Limited Co. (QPL) proposes a P95 billion, 1,230-megawatt natural gas-fired power plant in Mauban, Quezon, with commercial operations scheduled for the first quarter of 2031.

The project, named the CCGT San Francisco Power Plant, would combine a combined-cycle gas turbine (CCGT) power plant with a liquefied natural gas (LNG) import terminal, QPL said in its filing with the Department of Environment and Natural Resources (DENR).

“The power plant will primarily utilize natural gas supplied through imported LNG, with fuel oil available as a backup fuel source,” QPL said.

QPL’s 1,230-MW proposal would be more than twice the size of the 500-MW coal-fired plant operated by San Buenaventura Power Ltd. Co. (SBPL) in Mauban. Fuel oil holds the backup slot. The contingency plan is at least unambiguous.

What will occupy the 18.55-hectare site?

QPL’s DENR filing says the proposed CCGT San Francisco Power Plant would occupy an 18.55-hectare site comprising:

  • Onshore LNG regasification and storage facilities
  • A power plant
  • A seawater system
  • Electrical interconnection facilities
  • An LNG jetty

QPL said the site offered proximity to existing power facilities and supporting infrastructure, access to seawater needed for plant operations, available land for future expansion, and a connection to the transmission network.

According to the filing, the plant would connect to the Luzon grid through National Grid Corp. of the Philippines’ 230-kilovolt transmission network, using a 31-kilometer transmission line.

What is the construction schedule?

QPL’s filing sets three dates:

  • Construction start: second quarter of 2027
  • Construction completion: fourth quarter of 2030
  • Commercial operations: first quarter of 2031

How does the DoE auction fit?

The San Francisco Power Plant is among the projects proposed by 10 prequalified companies participating in the Department of Energy’s (DoE) first mid-merit natural gas capacity auction, the DoE said.

The auction seeks to secure 3,840 MW of gas-fired capacity nationwide from 2026 to 2031, including 2,900 MW allocated to Luzon.

The Luzon allocation breaks down as follows:

  • 1,400 MW targeted for delivery in 2026
  • Another 500 MW targeted for delivery in 2027
  • 1,000 MW targeted from new power facilities in 2031

The government considers natural gas a transition fuel. It says gas can support electricity supply and grid stability as the country increases renewables’ share of its power generation mix.

Who is behind QPL?

QPL is wholly owned by Thailand’s Electricity Generating Public Company Limited (EGCO Group), an independent power producer, according to the filing.

QPL also owns and operates an existing coal-fired power plant in Mauban. It is affiliated with SBPL, which operates a separate 500-MW coal-fired power plant in the municipality.

SBPL is a joint venture between Meralco PowerGen Corp. and an EGCO Group subsidiary, with ownership interests of 51% and 49%, respectively.

SBPL’s San Buenaventura facility began commercial operations in September 2019. It was the first coal-fired power plant in the Philippines to use supercritical boiler technology.

The DoE auction is the next public test for QPL. A second-quarter 2027 construction start is the next physical milestone. Until those steps happen, the P95 billion plant is still a filing, not a generator.

Source: bworldonline.com

natural-gas lng-terminal combined-cycle-power-plant mauban philippines

Share this article:

More from Amara Osei

Amara Osei

Show full bio

Market editor covering companies, deals and strategy in construction industry, architecture, interior design at Built Current.

354 articles

More projects

« Previous articleNext article »