Palace advances Agus-Pulangi rehab, flood pumps and bridge projects
Palace advances Agus-Pulangi rehab, flood pumps and bridge projectsschauhi / pixabay

Construction

Palace advances Agus-Pulangi rehab and flood-control works

The Palace reviews a 25-year Agus-Pulangi partnership, seven flood-pump deadline changes, Samal bridge funding issues and a five-campus dormitory proposal.

Author
By Marcus Bennett
Filed
Length
3 min read

Key takeaways

  • Agus-Pulangi rehabilitation would restore 1,001.96 MW and lift annual output to 4,305 GWh.
  • PSALM received three proposals, targets a private partner by December and expects rehabilitation to start in 2027.
  • Seven remaining pumping stations face a proposed May 31, 2027 completion deadline.
  • The Samal Island-Davao City Connector is a 3.98-km, four-lane cable-stayed bridge with unresolved funding and implementation issues.
  • Project BALAY covers five state campuses, with each dormitory estimated at P165.6 million.

The proposed rehabilitation of the Agus-Pulangi Hydropower Complex would restore generating capacity to 1,001.96 megawatts and increase annual output to 4,305 gigawatt-hours from 3,746 gigawatt-hours, the Presidential Communications Office said in a Wednesday statement.

What changes at Agus-Pulangi?

The administration said the project would support a more reliable electricity supply for households and businesses in Mindanao. For delivery teams, the proposal couples that restoration target to a capped tariff, a possible second 25-year term and a defined partner-selection timetable.

The project would proceed through a proposed 25-year partnership between the Power Sector Assets and Liabilities Management Corp. (PSALM) and a consortium of San Miguel Global Power Holdings Corp. and Sta. Clara International Corp., the Palace said.

The agreement could be extended for another 25 years, subject to government approval. The proposed tariff would be capped at P4 per kilowatt-hour, pending approval by the Energy Regulatory Commission, according to the PCO.

The PCO set out four elements of the selection timetable:

  • PSALM has received three unsolicited proposals for the project.
  • Two proposals remain under evaluation.
  • The government targets the selection of a private partner by December.
  • Rehabilitation works are expected to begin in 2027.

Those dates place partner selection before the stated construction start. They also leave both the possible extension and the P4 tariff ceiling conditional on government and regulatory approval.

What changes for the remaining pumping stations?

The council reviewed a proposal to extend the completion deadline for seven remaining pumping stations under Phase 1 of the Metro Manila Flood Management Project to May 31, 2027. Seven stations remain against an original target of 38 facilities, the PCO said.

In its statement, the PCO put the condition plainly: “The extension would be the second and final one and would not alter the project’s approved scope or cost.”

For delivery teams, this is a timetable adjustment rather than a programme redesign. The PCO said the extension would protect the approved physical scope and cost while giving the seven remaining stations more time.

What is blocking the Samal bridge?

President Ferdinand R. Marcos, Jr. directed the Department of Public Works and Highways to resolve funding and implementation issues affecting the Samal Island-Davao City Connector, according to the PCO.

The instruction gives the department two defined assignments: address the funding and address the implementation. The PCO described the connector as a 3.98-kilometer, four-lane cable-stayed bridge linking Davao City and Samal Island.

How would Project BALAY finance dormitories?

The council reviewed Project BALAY, a pilot initiative to build dormitories in five state universities and colleges in partnership with the Commission on Higher Education and the Pag-IBIG Fund, according to the PCO.

Each dormitory is estimated to cost P165.6 million. The government would provide either a 30% or 10% upfront payment, while Pag-IBIG would finance the balance, the PCO said.

  • Under the 30% upfront option, annual government payments beginning in 2028 would be P61.56 million over nine years at a 3% interest rate.
  • Under the 10% upfront option, annual government payments beginning in 2028 would be P82.58 million over nine years at a 3% interest rate.

The financing split is defined, but the authority to proceed is not. Project BALAY still requires presidential approval, concurrence from the Monetary Board and forward obligational authority from the Department of Budget and Management, the PCO said.

December is the power package’s next dated milestone, with the government targeting a private Agus-Pulangi partner by then and rehabilitation works expected in 2027. The pumping stations now have a proposed deadline of May 31, 2027, while BALAY and the bridge remain tied to the approvals and funding decisions identified by the Palace.

Source: bworldonline.com

hydropower-rehabilitation flood-management public-infrastructure bridge-construction public-private-partnership

Share this article:

More from Marcus Bennett

Marcus Bennett

Show full bio

Correspondent covering money, funding and market shifts around construction industry, architecture, interior design at Built Current.

328 articles

More projects

« Previous articleNext article »