Spain’s 935 MW transmission tender leads renewable energy roundup
Spain’s 935 MW grid-access tender, GRS’s 35 MW Corvera solar plant and Salka Energy’s $17.65 million Cabazon Wind Farm refurbishment lead this roundup.
- Section
- Green Building
- Author
- By Elena Vasquez
- Filed
- Length
- 3 min read
Key takeaways
- Spain opened a competitive tender for 935 MW of transmission access in Teruel province for renewable energy and storage.
- Corvera reached provisional acceptance at 35 MWdc with 50,070 panels across 55 hectares in Murcia.
- Corvera is GRS’s 40th Spanish solar project and third for Everwood Capital, whose portfolio is about 1.1 GWdc.
- $17.65 million from XRA will fund Salka Energy’s refurbishment of the 37.4 MW Cabazon Wind Farm in California.
- Cabazon and the neighboring 20 MW Edom Hills project total 57.4 MW and 145,000 MWh of projected annual generation.
By Elena Vasquez
Spain’s Ministry for the Ecological Transition has put 935 MW of electricity transmission access up for competitive allocation in Teruel province. The tender lets renewable-energy and battery-storage developers compete for grid-connection rights required for new generation and storage investments.
What does the 935 MW tender cover?
The 935 MW concerns transmission access, not awarded generation capacity or projects already under construction. Successful bidders must still meet applicable development, permitting and grid-connection requirements, according to the Ministry.
The Ministry says the process will make transmission capacity available to qualifying projects in Teruel. Its announcement leaves individual project sizes, investment commitments, storage duration and commercial operation dates unspecified.
What does the tender change for developers?
That makes the tender a gate to the provincial transmission network rather than a commitment to build 935 MW of plants. Developers compete for access first; project delivery remains conditional on later approvals and connection work.
The Ministry has set the scale of the grid opportunity without publishing its underlying pipeline. The announcement therefore fixes the size of the available connection allocation, but not how much new renewable capacity the tender will ultimately add.
What has GRS completed at Corvera?
GRS, a Spanish engineering contractor, has secured provisional acceptance for the 35 MWdc Corvera solar power plant in Murcia. Everwood Capital developed the project.
Corvera comprises 50,070 photovoltaic panels across 55 hectares. The plant uses PV Hardware’s Monoline+ 2V solar tracking systems.
GRS also constructed a 30/132 kV step-up substation. The contractor built associated 132 kV overhead and underground transmission infrastructure.
Corvera is GRS’s 40th completed solar project in Spain and its third for Everwood Capital. Earlier collaborations include the 167 MWdc Carmen solar cluster in Seville and the 50 MWdc Desafio Solar project in Zaragoza.
Together, the three developments represent 252 MWdc of solar capacity. Everwood manages a photovoltaic portfolio of approximately 1.1 GWdc, roughly 31 times Corvera’s capacity.
How is Salka Energy financing Cabazon?
Salka Energy has secured $17.65 million in financing from XRA, an affiliate of X-Caliber Rural. The money will refurbish Salka’s 37.4 MW Cabazon Wind Farm in California.
Salka expects the refurbished project to generate 95,000 MWh annually. The company says that output will supply more than 15,000 homes and avoid approximately 41,000 tonnes of CO₂ emissions.
Salka’s refurbishment retains 50 steel towers, their foundations and 150 fiberglass blades. The work is defined at component level, from foundations to blades.
Riverside Public Utilities will purchase Cabazon’s electricity. That contract gives the refurbished output a named off-taker.
What does the neighboring wind project add?
Salka also acquired the neighboring 20 MW Edom Hills wind project in April 2026. Salka expects Edom Hills to produce 50,000 MWh annually after refurbishment.
Together, Cabazon and Edom Hills represent 57.4 MW of capacity and projected annual generation of 145,000 MWh. The April acquisition therefore extends Salka’s California position beyond the project covered by XRA’s loan.
What comes next?
Spain’s tender now moves to bidder selection, while its missing project details leave the eventual generation schedule unsettled. Corvera has reached provisional acceptance. Cabazon and Edom Hills still depend on their planned refurbishments before Salka’s 145,000 MWh annual forecast becomes operating output.
Source: greentechlead.com