National Grid's £550m Humber-to-Midlands pylon line clears planning hurdle
The Planning Inspectorate has accepted National Grid's plans for a 90km, £550m overhead line from Birkhill Wood to High Marnham. Laing O'Rourke is already on board.
- Section
- Construction
- Author
- By Priya Raman
- Filed
- Length
- 2 min read
Key takeaways
- Planning Inspectorate accepted plans for a 90km, 400kV overhead line estimated at £550m-£553m
- Laing O'Rourke is principal contractor for enabling works along 46km of the route
- Birkhill Wood substation got planning permission in February 2026; High Marnham followed in June
- Construction is expected to begin in 2028, with the connection operational in 2031
- The project is part of National Grid's Great Grid Upgrade for offshore wind capacity
National Grid's £550m Humber-to-Midlands electricity upgrade has cleared its first planning hurdle: the Planning Inspectorate has accepted the application for a 90km overhead power line. The decision moves the North Humber to High Marnham project a step closer to construction.
The scheme will build a new 400kV transmission route (the highest voltage tier on Britain's grid) between Birkhill Wood, near Hull, and High Marnham in Nottinghamshire. Laing O'Rourke is already mobilising as principal contractor for enabling works along 46km of the overhead line route.
What does it cost, and where does the money go?
National Grid's earlier strategic assessment put the capital cost of the wider scheme at £553m. That breaks down into £338m for overhead transmission lines and £215m for associated substation works.
The two new substations anchor each end of the route. They are being delivered through separate planning applications, and both have already cleared consent:
- Birkhill Wood — planning permission granted in February 2026
- High Marnham — planning permission granted in June
The line itself involves more than pylons. Plans include major diversions and realignments of existing high-voltage routes, plus access roads, temporary construction compounds, highway works and environmental mitigation.
When will the power flow?
The timeline is fixed, subject to development consent (the UK's Nationally Significant Infrastructure Project approval, granted by the government on the Inspectorate's recommendation). Construction of the transmission line is expected to begin in 2028. The new connection should be fully operational in 2031.
That's roughly a three-year build for 90km of steel and cable across the Humber region and the Midlands edge.
Why the line matters
The scheme forms part of National Grid's Great Grid Upgrade programme, designed to increase capacity for electricity generated by offshore wind farms and move more power south from the Humber region.
Monica Corso Griffiths, project director for North Humber to High Marnham, said: "The acceptance of our application is an important milestone for North Humber to High Marnham and reflects years of work developing our proposals and engaging with people across the project area."
Corso Griffiths framed the project against rising demand: "As demand for electricity continues to grow and increasing amounts of offshore wind connect to the network, investment in electricity infrastructure will play an important role in ensuring power can be transported efficiently to homes, businesses and public services."
What changes for the grid and the contractors?
For contractors, the acceptance triggers the next procurement and enabling-works phase, with Laing O'Rourke holding the 46km enabling package already. For the grid, acceptance starts the examination clock: the Inspectorate will now scrutinise the application before a consent decision, keeping the 2028 start date and 2031 energisation within reach — milestones National Grid needs if the Great Grid Upgrade is to carry Humber offshore wind south on schedule.
Source: Construction Enquirer