MoD lines up £500m Portsmouth naval jetty rebuild
MoD lines up £500m Portsmouth naval jetty rebuildWikiImages / pixabay

Construction

MoD plots £500m rebuild of Portsmouth's Fountain Lake Jetty

The Defence Infrastructure Organisation wants contractors for a £500m, four-phase rebuild of the 650m Fountain Lake Jetty at Portsmouth Naval Base, with tenders due June 2027.

Author
By Amara Osei
Filed
Length
2 min read

Key takeaways

  • The MoD is sourcing contractors for a £500m rebuild of the 650m Fountain Lake Jetty at Portsmouth Naval Base
  • The main contract is expected to run from March 2028 until December 2037
  • The scheme will deliver three tidal maintenance berths, up from the two initially required
  • Formal tenders are scheduled for June 2027; market engagement responses close 26 February 2027
  • The competition is open only to contractors from NATO member countries

The Ministry of Defence wants contractors for a £500m rebuild of Fountain Lake Jetty at Portsmouth Naval Base — one of the largest marine construction projects on the Royal Navy's books.

The Defence Infrastructure Organisation (DIO) has unveiled plans to replace the ageing 650m-long structure outright. Built in the 1950s and 1960s, the jetty provides tidal maintenance berths for the Navy's surface fleet. It has, in DIO's assessment, reached the end of its working life.

The timing isn't sentimental. A new generation of larger escort warships, built to support the UK's aircraft carrier strike group, needs berths that a 1950s structure can't offer. The rebuild will ultimately deliver three tidal maintenance berths, up from the two initially required.

What does the scheme involve?

Work will run in four phases, covering the jetty's 375m eastern section and 275m western section. The scope includes:

  • Extensive demolition and construction of new piled jetty structures
  • Dredging
  • Replacement buildings
  • Upgraded water, power and communications infrastructure
  • Strengthened and raised impounding walls
  • New access routes and flood defence improvements

The winning contractor won't just build. It will also help the project team develop the preferred design and secure the marine licences before delivering the main works.

The investment sits inside Project Royal Oak, the wider programme to modernise Britain's naval bases and improve maintenance facilities for the surface fleet.

When will contracts go out?

The procurement clock is already running. DIO plans to issue a market engagement questionnaire before the end of this year, with an industry day to follow in the first quarter of 2027. Firms have until 26 February 2027 to respond to the preliminary market engagement exercise.

Formal tenders are scheduled for June 2027. The main contract is expected to run from March 2028 until December 2037 — nearly a decade of marine construction, dwarfing most civilian waterfront jobs of similar character.

There's one geopolitical wrinkle: the competition is open only to contractors from NATO member countries. Interested firms can contact Robyn Murphy at the MoD for further details.

With a £500m budget, a ten-year contract window and a live naval base as the worksite, the Fountain Lake job will test whoever wins it. Bidders have until early 2027 to decide whether they want that test.

Source: Construction Enquirer

marine-construction naval-infrastructure ministry-of-defence portsmouth-naval-base fountain-lake-jetty

Share this article:

More from Amara Osei

Amara Osei

Show full bio

Market editor covering companies, deals and strategy in construction industry, architecture, interior design at Built Current.

354 articles

More projects

« Previous articleNext article »