£600m design race looms for £3.7bn Windermere clean-up
£600m design race looms for £3.7bn Windermere clean-upDatingjungle / unsplash

Construction

United Utilities Prepares £600m Design Race for £3.7bn Windermere Clean-Up

United Utilities will issue a tender in early November for a £600m design and integration contract driving its £3.7bn Windermere wastewater overhaul, with tunnelling at its core.

Author
By Elena Vasquez
Filed
Length
2 min read

Key takeaways

  • United Utilities will launch a £600m design and integration race for a £3.7bn Windermere wastewater programme
  • Formal tender notice expected in early November after preliminary market engagement
  • Initial design phase worth £60m-£100m; programme includes up to 138km of new sewers and 35km of highway runoff interception
  • More than 70 options narrowed to two preferred solutions by consultants Jacobs and Mott MacDonald
  • Full build would take around seven years; the alternative is £2.5bn of upgrades still discharging into the lake

United Utilities is preparing to launch a £600m design and integration competition for its proposed £3.7bn overhaul of wastewater infrastructure around Windermere. A formal tender notice is expected in early November, following preliminary market engagement.

The appointment will help shape one of the water sector's biggest emerging construction programmes. The scope includes major tunnelling, new sewers, pumping infrastructure and advanced treatment works.

How does the money break down?

The initial design and pre-delivery phase is expected to be worth around £60m to £100m. Longer-term integration and delivery support could take the total appointment to £600m — roughly the price of ten initial design phases, and a fraction of the full £3.7bn construction bill.

The programme sits under United Utilities' "Only Rainwater into Windermere" initiative. The utility has narrowed more than 70 options down to two preferred solutions. Both involve intercepting wastewater currently entering the lake catchment and transferring it through new underground pipelines for advanced treatment.

What would actually get built?

The wider proposals include:

  • Extensive tunnelling
  • Up to 138km of new sewer network
  • Around 35km of highway runoff interception
  • 37 hectares of sustainable drainage

Thousands of homes, holiday properties and other premises currently relying on private treatment systems could also be connected to the public sewer network.

Consultants Jacobs and Mott MacDonald have carried out the feasibility work for the preferred options. United Utilities believes the full programme would cost up to £3.7bn and take around seven years to build once detailed design, planning, environmental and regulatory approvals are secured.

Tunnelling is expected to play a major role in limiting disruption across the sensitive Lake District landscape.

Why now?

United Utilities chief executive Louise Beardmore said: "After assessing more than 70 options, two have been selected to progress into detailed design, with the potential to deliver lasting environmental, social and economic benefits across the catchment."

The alternative, according to the utility, is to spend around £2.5bn over coming decades upgrading existing infrastructure — while still allowing treated wastewater to discharge into the lake. In other words, the cheaper path keeps the pollution problem in place; the £3.7bn plan is designed to remove treated discharges from the catchment altogether.

With the tender notice weeks away, design and engineering firms now face a decision on whether to compete for a fee pool that starts at £60m-£100m but could grow tenfold as the programme moves toward construction.

Source: Construction Enquirer

united-utilities windermere wastewater-infrastructure tunnelling sewer-network

Share this article:

More from Elena Vasquez

Elena Vasquez

Show full bio

Senior reporter covering money, funding and market shifts around construction industry, architecture, interior design at Built Current.

183 articles

More projects

« Previous article