Sisk lands £37m Birkenhead regeneration deal
Sisk lands £37m Birkenhead regeneration dealEngin_Akyurt / pixabay

Urbanism & Planning

Sisk wins £37m contract to unlock Birkenhead's 1,600-home Borough Yard

John Sisk has won a £37m Wirral Council contract for enabling works at Borough Yard, Birkenhead, where programme costs have climbed to £66m amid inflation and drainage costs.

Author
By Elena Vasquez
Filed
Length
2 min read

Key takeaways

  • John Sisk won a £37m fixed-price enabling works contract for Birkenhead's Borough Yard scheme.
  • Wirral Council's wider enabling works budget has risen from £57m to £66m.
  • Liverpool City Region Combined Authority will cover an £8.9m funding gap.
  • A further £13.7m is earmarked for United Utilities sewer diversions and stormwater storage.
  • The masterplan carries hybrid consent for up to 1,600 homes over a 10-15 year build-out.

John Sisk has landed a £37m fixed-price contract to prepare a former gasworks and railway site in Birkenhead for a new 1,600-home neighbourhood. Wirral Council has approved the enabling works deal for the Borough Yard regeneration scheme, formerly known as Hind Street Urban Village.

The site sits between Birkenhead Central and Green Lane stations. Sisk's remit covers major ground remediation and engineering works, construction of a new active travel corridor and the first section of the planned Dock Branch South linear park.

Why has the budget grown?

The wider enabling works programme has seen costs jump from £57m to £66m — a rise of roughly 16 per cent — because of inflation, delays and rising drainage infrastructure costs. To put that in perspective, the increase alone is more than five times the £2.9m development management agreement Wirral councillors approved with Ion Property Developments, the firm overseeing the regeneration.

The Liverpool City Region Combined Authority has agreed to plug the resulting £8.9m funding gap.

Beyond that, a further £13.7m has been earmarked for separate United Utilities works involving major sewer diversions and an underground stormwater storage tank. Cadent gas infrastructure will also need relocating.

What has been delayed to save money?

To contain costs, highway realignment works at Kings Square and part of the Dock Branch South park have been pushed back to 2027. These works are estimated at a further £12m — money that nearly matches a third of Sisk's current contract — and could eventually be added to the contractor's deal.

That structure matters. It means Sisk's £37m award could grow toward £49m if the deferred package joins its scope.

How big is the wider plan?

The Borough Yard masterplan has hybrid planning consent for up to 1,600 homes, commercial space, community facilities and new public areas. Development is expected to take between 10 and 15 years, with the initial enabling works intended to unlock at least 633 homes — nearly 40 per cent of the total — in the first phase.

The combined figures show the scale of the public commitment. Once the £66m programme, the £13.7m United Utilities package and the potential £12m deferred works are counted, total infrastructure spending approaches £92m before a single home is built.

For now, the focus shifts to Sisk's remediation and engineering works, which will determine how quickly the first 633 homes can reach the market.

Source: Construction Enquirer

borough-yard birkenhead john-sisk urban-regeneration infrastructure-works

Share this article:

More from Elena Vasquez

Elena Vasquez

Show full bio

Senior reporter covering money, funding and market shifts around construction industry, architecture, interior design at Built Current.

400 articles

More projects

« Previous article