Landsec shelves £1.5bn Lewisham Shopping Centre redevelopment
Landsec has shelved its £1.5bn Lewisham Shopping Centre redevelopment after cost inflation and a council demand for more affordable housing blocked delivery.
- Section
- Urbanism & Planning
- Author
- By Priya Raman
- Filed
- Length
- 2 min read
Key takeaways
- Landsec has shelved the £1.5bn Lewisham Shopping Centre redevelopment
- The scheme had formal approval in July and included 1,744 homes, 660 student beds and 445 co-living rooms
- Lewisham's new Green administration demanded more affordable housing; the plan had 98 social rent homes
- Work had been due to start next year; towers of up to 35 storeys were planned
- Landsec has owned the existing centre for more than 20 years and will keep operating it
Landsec has shelved its £1.5bn redevelopment of Lewisham Shopping Centre after rising construction costs and a council stand-off over affordable housing killed its route to delivery.
Work had been due to start next year. The south east London scheme would have replaced the 1970s mall with a new shopping district and residential towers rising to 35 storeys.
The consented masterplan (the approved overall site plan) packed in substantial numbers:
- More than 1,700 homes, in a final total of 1,744
- 660 student beds
- 445 co-living rooms
- A 500-capacity music venue
- A rooftop meadow
What broke the scheme?
Two forces converged. First, the developer needed Lewisham Council's support to assemble land, including taking control of the neighbouring former Citibank tower, Lewisham House. The borough's new Green administration refused to back that step without a significant increase in affordable housing, forcing a rethink of the consented scheme.
Second, the economics soured. Landsec said higher interest rates, construction inflation and new building regulations had already made London development exceptionally challenging. The demand for more affordable homes would require a material change to its proposals.
"This position, combined with the exceptionally difficult economic conditions, mean that we no longer see a sufficiently certain route to delivery and have taken the difficult decision to deprioritise the redevelopment of Lewisham Shopping Centre," the developer said.
How did the politics shift?
Councillors backed the plans under the previous Labour administration last year, with formal approval following in July.
The scheme included 98 social rent homes (homes let at below-market rents set by government formula) and 231 discounted rental homes for key workers within the total of 1,744 homes — a ratio the new council leadership found too thin.
Mayor of Lewisham Liam Shrivastava, who backed a campaign against the redevelopment before taking office, said the social housing offer needed to improve. "This administration is laser focused on delivering genuinely affordable housing and I've consistently said the level of social rent homes in this scheme needed to increase," he said.
But he acknowledged the wider development squeeze. "The fact is the conditions for such projects are simply not favourable right now," Shrivastava said.
What does this change for Lewisham?
The immediate losers are the 1,700-plus homes, the student beds and the music venue, none of which now have a delivery date. The 1970s mall stays. Preparations for construction had already prompted Boots to relocate, while NatWest had announced plans to follow — churn that happened without a new district arriving to replace what left.
Landsec will continue operating and investing in the existing shopping centre, which it has owned for more than 20 years. That signals a hold-and-manage stance rather than an exit, and it leaves the door open to a revised scheme if construction costs fall or a fresh affordable housing deal can be struck with the Green administration.
Source: Construction Enquirer
More from Priya Raman
Show full bio
News editor covering people, launches and day-to-day practice in construction industry, architecture, interior design at Built Current.