London Waste-to-Energy Contract Balloons 56% to £1.25bn in Acciona Settlement
Acciona's Edmonton EcoPark Energy Recovery Facility contract jumps from £799m to £1.25bn, with completion pushed to December 2029 after a £572m claims battle.
- Section
- Construction
- Author
- By Grace Kim
- Filed
- Length
- 2 min read
Key takeaways
- The Edmonton EcoPark contract value rose 56%, from £799m signed in January 2022 to £1.25bn.
- Acciona submitted £572m in claims over delays, design changes and employment terms.
- Contractual completion moves from September 2026 to December 2029.
- The project is over 60% complete, with around £700m already spent.
- Cancelling could have added £100m a year to seven boroughs' waste costs by 2030/31.
Spanish contractor Acciona has secured a £451m increase on its north London waste-to-energy contract, pushing the value of the Edmonton EcoPark Energy Recovery Facility from £799m to £1.25bn — a 56% jump since the deal was signed in January 2022.
The settlement with the North London Waste Authority follows a major claims battle. Acciona had submitted claims totalling £572m linked to delays, changes to the works and disputes over employment conditions. It also pushes contractual completion back to December 2029, more than three years later than the original September 2026 handover date.
A council report reveals Acciona had previously been forecasting completion as late as 2032. The contractor argued that delays attributable to the client meant the contractual completion date was effectively no longer fixed. The authority rejected that position.
What were the disputes about?
Four major disputes had been referred to arbitration. They covered:
- The use of National Agreement for the Engineering Construction Industry (NAECI) employment terms
- Changes to the administration building design
- A steam turbine design dispute
- Compensation arising from a suspension agreement between June 2024 and January 2025
The authority said the project, which began construction in 2022, became steadily impacted by world events, causing significant inflation, higher interest rates, increased material costs and labour shortages. A lack of skilled subcontractors for mechanical and electrical works — including critical systems such as boilers and flue-gas treatment equipment — has been a significant issue, driving delays, disputes and rising costs for Acciona.
What does the new deal change?
Under the revised agreement, Acciona takes on greater responsibility for future inflation, wage increases, industrial relations and productivity risks. The contractor will also receive relief from delay damages until six months after the contractual takeover date. The settlement is intended to end the outstanding arbitration proceedings and establish a revised construction programme, with the formal agreement expected to be signed in December.
Progress on site is already substantial. The project is now more than 60% complete, with around £700m already spent. Workforce numbers have risen from about 200 at the start of this year to more than 400, and the turbine and generator are now installed.
Why not just cancel it?
The new plant will replace the ageing Edmonton incinerator and has been designed to process up to 700,000 tonnes of residual waste annually, generating electricity and supplying heat to homes and businesses. The authority said abandoning the scheme would be more expensive than pressing ahead, potentially adding £100m a year to the seven participating boroughs' waste costs by 2030/31.
Authority chair Cllr Jacob Cable said: "Cancelling the project at this stage would impose significantly greater costs on the boroughs."
The authority said the revised contract would provide greater cost certainty and ensure Acciona remains responsible for delivering and commissioning the completed plant. If the December signing stays on schedule, north London's seven boroughs will have a fixed price and a firm date — nearly two decades of rising costs compressed into one settlement.