Council to rebid A38 job after Octavius price busts budget
Council to rebid A38 job after Octavius price busts budgetreal-napster / pixabay

Construction

North Somerset rebids £24m A38 highways contract after price rise

North Somerset Council will retender a £24m A38 contract after Octavius’s price exceeded its funding position. A fixed-price NEC4 Option A tender starts in January, with work due in summer 2027.

Author
By Marcus Bennett
Filed
Length
3 min read

Key takeaways

  • North Somerset Council will retender the £24m A38 highways contract.
  • Octavius was appointed in 2025 under a two-stage design-and-build deal.
  • Construction is benchmarked at £23.7m against an original allowance of around £18m.
  • Forecast delivery spending reaches £33.4m after additional costs and contingency.
  • Procurement starts in January; bids are assessed in April; work is expected in summer 2027.

By Marcus Bennett

North Somerset Council will retender a £24m A38 highways contract after Octavius’s construction price exceeded the council’s approved funding position, according to council papers.

North Somerset Council papers say Octavius was appointed in 2025 under a two-stage design-and-build deal. The contractor was appointed to develop the scheme and agree a Stage 2 construction price. Council papers state that “the contractor’s estimate overshot both the original budget assumptions and the approved funding position.”

The price gap has forced the council to reopen the construction phase rather than complete the original appointment. Its response is a new fixed-price procurement, with a later start for the roadworks.

Why did the A38 contract price exceed the budget?

A benchmarking review by Rider Levett Bucknall examined the gap between Octavius’s estimate and the council’s budget. It found the difference “could not be fully explained by inflation, utilities, traffic management, design changes or supply-chain pressures.”

That finding rules out the listed pressures as a complete explanation for the excess. The review did not fully account for the difference, and the council has rejected the original target-cost route. That is a reset of procurement terms, not a routine adjustment to a small allowance.

What changes under the fixed-price NEC4 Option A?

North Somerset Council says it now plans to ditch the target-cost route and retender the works under a fixed-price NEC4 Option A contract. The original two-stage arrangement left Octavius to develop the scheme and agree its construction price at Stage 2. The replacement process asks bidders to commit to a fixed price during tender.

That shift moves price risk into the bid rather than leaving it open until after design. For contractors, the practical test is whether they can price the full construction package against the council’s current benchmark without reproducing the gap identified in the review.

The council’s latest benchmark puts construction at £23.7m. The original tender assumptions had allowed around £18m for construction. The higher benchmark now forms the reference point for new bids, while the move to a fixed price determines how much of that difference bidders must absorb.

The council’s wider forecast adds utility diversions, project management, council costs and contingency to the construction figure. Together, they take forecast delivery spending to £33.4m. The £24m A38 job therefore sits within a larger delivery envelope, and the construction figure alone does not describe the council’s full exposure.

When will the A38 work proceed?

A fresh procurement is due to start in January, according to North Somerset Council’s timetable. Bids will be assessed in April, and a new contractor is expected to be appointed in May or June. Work is now expected to start in summer 2027, around six months later than planned.

That timetable compresses the period available for the successful contractor to prepare for construction. The retendered works cover five locations along the A38, including work around Bristol Airport, Langford and Sidcot.

The original Octavius deal included a break clause allowing the council to retender the construction phase if the agreed price proved unacceptable. North Somerset Council says the current rebid follows that contractual route after the Stage 2 price breached the funding assumptions. The clause has returned the five-location delivery programme to the market.

What will determine whether the reset works?

The new procurement will carry a £23.7m construction benchmark, a £33.4m total delivery forecast and a summer 2027 start. The original construction allowance of around £18m no longer matches the council’s current cost assessment.

For contractors, the central test is whether the fixed-price tender can close the gap identified by Rider Levett Bucknall without relying on the cost pressures its review could not fully explain. For the council, the May or June appointment will determine whether the reset can hold the £33.4m forecast while preserving a summer 2027 start. The new terms will be judged against those two hard outputs.

Source: Construction Enquirer

a38 north-somerset-council highways construction-procurement nec4-contracts

Share this article:

More from Marcus Bennett

Marcus Bennett

Show full bio

Correspondent covering money, funding and market shifts around construction industry, architecture, interior design at Built Current.

343 articles

More projects

« Previous articleNext article »