Gateway 2 approval times improve to 20 weeks
Gateway 2 approval times improve to 20 weeksskorchanov / pixabay

Construction

Gateway 2 Approval Times Fall to 20 Weeks as Levy Rush Recedes

BSR cut Gateway 2 median approval times to 20 weeks as applications fell from 64 to six after the Building Safety Levy took effect on 1 October.

Author
By Marcus Bennett
Filed
Length
2 min read

Key takeaways

  • Median Gateway 2 approval time fell from 23 to 20 weeks in the 12 weeks to 1 November.
  • New applications dropped from 64 in September to six in October after the Building Safety Levy began on 1 October.
  • BSR approved 40 of 42 new-build and conversion applications covering 9,453 homes.
  • 183 applications covering 39,843 homes remain in progress; complex schemes wait 35 weeks.
  • Overall Gateway 2 approval rate stands at 92 per cent, with 370 of 403 applications approved.

Gateway 2 approval times for new high-rise buildings and conversions have fallen to 20 weeks, down from 23 weeks in the previous reporting period, according to the latest figures from the Building Safety Regulator covering the 12 weeks to 1 November.

The improvement follows a dramatic collapse in demand. New submissions dropped from 64 in September to just six in October, after the Building Safety Levy came into force on 1 October. BSR attributes the fall to a dip following the pre-levy surge, when developers raced to lodge applications ahead of the new charge.

That rush had real operational consequences for the regulator. It forced BSR to bolster its teams and triage applications as incoming schemes outpaced decisions.

What did the regulator approve in the latest period?

The 12-week figures to 1 November show BSR approved 40 of 42 new-build and conversion applications, covering 9,453 homes. The median approval time for these schemes now stands at 20 weeks.

Complex schemes tell a different story. Approval times for these projects run at 35 weeks, and 35 complex cases remain under assessment.

How large is the remaining backlog?

The queue remains substantial. Some 183 applications covering 39,843 homes are still in progress. Over the rolling period, 96 applications arrived against just 42 decisions — a gap that keeps pressure on turnaround times even as the headline median improves.

For developers of standard high-rise schemes, the numbers signal a regulator regaining ground. For those with complex projects, the 35-week median sets a more demanding programme assumption.

What is happening with legacy remediation cases?

Separately, BSR has cut its outstanding legacy remediation applications dating from 2024 to just five, down from 42 at the start of the year. Four of the five relate to a single development, and all five are targeted for clearance by the end of November.

These form part of a wider workload of 292 active remediation cases that continues to run through the regulator's system.

What is the overall approval rate?

Across all Gateway 2 categories, the regulator approved 370 of 403 applications over the period, taking its overall approval rate to 92 per cent.

The combination of a falling intake and sustained decision output suggests the 20-week median could hold or tighten further — provided the post-levy dip in submissions, which BSR itself reads as temporary, does not reverse.

Source: Construction Enquirer

gateway-2 building-safety-regulator high-rise-construction building-safety-levy construction-approvals

Share this article:

More from Marcus Bennett

Marcus Bennett

Show full bio

Correspondent covering money, funding and market shifts around construction industry, architecture, interior design at Built Current.

328 articles

More projects

« Previous articleNext article »