Fluor wins $4B Kentucky data center construction contract
TeraWulf awarded Fluor a definitive EPC contract for three buildings at its $4 billion Justified Data Campus in Hawesville, with phased service from late 2027 through Q2 2028.
- Section
- Construction
- Author
- By Amara Osei
- Filed
- Length
- 2 min read
Key takeaways
- TeraWulf awarded Fluor a definitive EPC contract for three buildings at the $4 billion Justified Data Campus in Hawesville, Kentucky.
- Fluor received a March limited notice to proceed for master planning and preconstruction; early construction has begun.
- Phased ready-for-service completions are expected from late 2027 through Q2 2028.
- Google provided credit support for debt financing; Anthropic has about $19 billion in contracted lease commitments.
- Fluor did not disclose the contract value and expects Q4 award recognition after pricing the first two buildings.
By Amara Osei
TeraWulf has awarded Fluor a definitive engineering, procurement and construction contract for three data center buildings at its $4 billion Justified Data Campus in Hawesville, Kentucky. TeraWulf expects phased ready-for-service completions from late 2027 through the second quarter of 2028.
TeraWulf, an Easton, Maryland-based data center infrastructure developer, announced the award in a Nov. 4 news release. Early construction work at the Bluegrass State campus has already begun. Fluor secured a limited notice to proceed in March for master planning and preconstruction services. In August, state utility regulators approved an electric-service agreement for the project, Engineering News-Record reported.
What does Fluor’s expanded role cover?
TeraWulf said in a separate Nov. 4 release that Fluor’s expanded scope includes testing and commissioning. Fluor did not disclose the contract value. The company expects to recognize the award in the fourth quarter once it finalizes pricing for the first two buildings.
The project carries a $4 billion figure, a phased delivery schedule and a financing plan. Fluor has kept the contract value undisclosed. The company disclosure leaves one conspicuous blank.
“Fluor gives us the ability to scale execution without building a global engineering and construction organization internally,” said Paul Prager, chairman and CEO of TeraWulf, in the release. “Their engineering depth, procurement capabilities and access to skilled labor complement our team’s decades of experience developing energy infrastructure.”
Prager’s pitch is capacity, not novelty. Use Fluor’s global engineering bench; do not build a duplicate one in-house. Prager also framed the partnership as a complement to TeraWulf’s decades of energy-infrastructure experience.
How is the $4 billion campus financed?
TeraWulf secured credit support from Google for debt financing at the campus, according to the company’s release. Anthropic, an AI company, has about $19 billion in contracted lease commitments there. TeraWulf said the Google support, Anthropic leases and Fluor award together increase its construction execution capacity.
“Cost of capital is fundamental to infrastructure development,” said Patrick Fleury, chief financial officer at TeraWulf, in the announcement. “Strong investment-grade credit support strengthens the project’s financing profile.”
Fleury’s argument rests on cost of capital. TeraWulf’s release groups Google’s support, Anthropic’s leases and Fluor’s execution role within one delivery proposition.
When does the campus become operational?
- March: Fluor received a limited notice to proceed covering master planning and preconstruction services.
- August: State utility regulators approved the electric-service agreement, according to Engineering News-Record.
- Nov. 4: TeraWulf announced the definitive EPC contract; early construction had already begun.
- Late 2027–second quarter of 2028: TeraWulf expects phased ready-for-service completions, with testing and commissioning included in Fluor’s scope.
Fluor’s next financial marker is the fourth quarter, when it expects to recognize the award after finalizing pricing for the first two buildings. The longer watch concerns delivery: phased service must begin in late 2027 and run through the second quarter of 2028.