Garrison Architects to Pay for ADA-Noncompliant Door Hardware at Six Cherry Hill Schools

Garrison Architects will cover the cost of replacing ADA-noncompliant door pulls at Rosa, Beck and Carusi middle schools and four elementary schools in Cherry Hill, officials said Nov. 10.

Author
By Elena Vasquez
Filed
Length
2 min read

Key takeaways

  • Door pulls at seven Cherry Hill school entrances failed ADA accessibility standards, confirmed Nov. 10.
  • Garrison Architects accepted financial responsibility for replacing all noncompliant hardware.
  • Affected schools: Rosa, Beck and Carusi middle schools; Johnson, Barton, Kingston and Sharp elementary schools.
  • Board members questioned safeguards for future work funded by the Cherry Hill Tomorrow bond referendum.
  • Schimpf said the district monitors compliance with Cherry Hill Township's code office.

Garrison Architects has accepted financial responsibility for replacing door hardware that fails Americans with Disabilities Act (ADA) requirements at seven Cherry Hill school entrances, the district confirmed on Nov. 10.

The problem surfaced at the Nov. 10 Board of Education meeting, when district officials addressed concerns about the main entrance and newly constructed accessible cafeteria entrances at Rosa Middle School. Newly installed door pulls at those entrances don't meet accessibility standards.

Business Administrator Jason Schimpf explained the district's response. The district brought in its architectural firm, Garrison Architects, along with civil engineers, to investigate the concerns. Their review confirmed that some of the specified door hardware fell short of the standards.

Who pays for the fix?

Garrison Architects, not taxpayers. The firm has accepted financial responsibility for replacing the noncompliant hardware with door pulls that meet ADA requirements, and the district says it's working to complete the replacements as soon as possible.

The scope extends well beyond Rosa Middle School. Hardware will also be replaced at recently renovated entrances at:

  • Beck Middle School
  • Carusi Middle School
  • Johnson Elementary School
  • Barton Elementary School
  • Kingston Elementary School
  • Sharp Elementary School

What does this mean for the Cherry Hill Tomorrow bond?

Board members pressed officials on a bigger question: how will the district prevent similar problems in future construction funded through the Cherry Hill Tomorrow bond referendum?

Schimpf said district officials are continuing to work with Cherry Hill Township's code office and construction professionals to monitor compliance throughout the renovation process.

"I have full confidence in ensuring that all of our future projects are fully compliant with ADA," Schimpf said.

He added that when accessibility concerns are identified, the district's priority is to address them promptly.

The replacements are underway now, with Garrison Architects covering the associated costs — a stance that spares the district's bond budget and sets a precedent for how design errors get resolved as the larger renovation program moves forward.

Source: haddonfieldsun.com

ada-compliance school-renovations door-hardware accessibility construction-oversight

Share this article:

More from Elena Vasquez

Elena Vasquez

Show full bio

Senior reporter covering money, funding and market shifts around construction industry, architecture, interior design at Built Current.

384 articles

More projects

« Previous article