Alternergy plans P10 billion green bond program for renewables
Alternergy targets up to P10 billion from fixed-rate green bonds, starting with a P3 billion tranche in early 2027, to help fund P26 billion of wind and solar projects.
- Section
- Green Building
- Author
- By Elena Vasquez
- Filed
- Length
- 3 min read
Key takeaways
- Alternergy targets up to P10 billion in fixed-rate green bonds through a five-year shelf registration program.
- The initial tranche includes a P3 billion base offer and an oversubscription option of up to P1 billion, targeted for the first quarter of 2027.
- Alternergy has allocated approximately P26 billion for two solar farms and one wind power project.
- The company expects 311 MW of operating capacity by the end of 2026 and 873 MW by 2029, targeting 1,000 MW by 2030.
- Alabat’s 64-MW wind farm targets commercial operations in December, while Tanay’s 128-MW farm is scheduled for January 2027.
Alternergy Holdings Corp. plans to raise up to P10 billion through fixed-rate green bonds to help finance P26 billion in planned solar and wind investments.
At its annual stockholders’ meeting on Tuesday, Chairman Vicente S. Pérez, Jr. said the board approved a five-year shelf registration program. Alternergy targets the initial offering for the first quarter of 2027.
What does the bond program fund?
Alternergy plans to register the proposed bonds with the Securities and Exchange Commission and issue them in tranches over five years. The company targets a listing of the initial tranche on the Philippine Dealing & Exchange Corp. in the first quarter of next year.
The initial tranche combines a P3 billion base offer with an oversubscription option of up to P1 billion. On Alternergy’s stated figures, the full P10 billion shelf would cover about two-fifths of the P26 billion capital plan. The bonds alone therefore cannot fund all three projects.
Pérez told reporters at the sidelines of the annual meeting: “This is a P50,000-retail green [bond offering] to allow more Filipino professionals and families to participate in the green story.” He also said Alternergy has held advanced discussions with project lenders, with four banks competing to finance three projects.
Alternergy President Gerry P. Magbanua said the bond proceeds would help finance upcoming wind and solar projects awarded under the Department of Energy’s fourth green energy auction. Alternergy has allocated approximately P26 billion in capital expenditures to develop two solar farms and one wind power project.
Which projects will the bonds help fund?
The three planned developments are:
- A 140-megawatt (MW) solar-on-stilts project in Central Luzon.
- A 100-MW solar farm with a battery energy storage system in Mindanao.
- A 120-MW wind power project in Cebu.
Which projects are already generating?
Alternergy has advanced four renewable energy projects, two of which have begun commercial operations. The 28-MW Balsik solar farm in Bataan and the 4.6-MW Dupinga run-of-river hydropower plant in Nueva Ecija are among them.
Alternergy’s 64-MW Alabat wind farm in Quezon and 128-MW Tanay wind farm in Rizal have started generating commissioning revenues ahead of commercial operations. Alabat is scheduled to begin commercial operations in December, while Tanay is scheduled to start in January 2027.
How will Alternergy reach 1,000 MW?
Alternergy aims to expand its renewable energy portfolio to 1,000 MW by 2030 under its Triple Play Portfolio strategy. The strategy covers wind, solar and run-of-river hydropower.
The company expects operating capacity to reach 311 MW by the end of 2026 and 873 MW by 2029. “As our portfolio expands, we expect a significant increase not only in generating capacity, but more importantly, in electricity generation,” Magbanua said.
At the local bourse on Tuesday, Alternergy shares rose one centavo, or 1.54%, to 66 centavos apiece. The first-quarter 2027 bond offering and the two wind farms’ commercial start dates are the next milestones for Alternergy’s expansion from 311 MW at the end of 2026 to 1,000 MW by 2030.