€90m Glounthaune to Midleton track work nears completion
Iarnród Éireann says the €90 million second track to Midleton is largely built, with 2027 completion tied to Cork-wide re-signalling and a wider commuter programme.
- Section
- Construction
- Author
- By Amara Osei
- Filed
- Length
- 3 min read
Key takeaways
- The €90 million Glounthaune to Midleton second track is largely complete; overall completion is set for 2027.
- Construction began in September 2024, and the first new track was laid in September 2025.
- The project includes 7.5 km of new track, 20 retaining walls and more than 10 km of drainage.
- Phase 1 includes a €23 million platform 6 at Kent Station and is due for full completion in 2027.
- Phase 2 includes eight stations, a depot, electrification and a new fleet; its Railway Order Application is expected by end-2026.
Iarnród Éireann says main construction work on its €90 million second track between Glounthaune and Midleton is largely complete, and the company expects the overall project to finish in 2027.
That is the concrete milestone, not a completed regional upgrade. The track forms part of the wider Cork Area Commuter Rail Programme, and Iarnród Éireann ties completion in 2027 to re-signalling of the full Cork rail network.
What has been built?
Construction began in September 2024. Iarnród Éireann says an initial 12 months covered preparatory works, including laying the new track bed and repositioning the existing single track. The first piece of the new track was laid on programme in September 2025, and construction has progressed steadily since.
The project widened the Owennacurra River Bridge in Midleton and included work on several culverts, level crossings, cuttings and embankments. All construction ran alongside a live operational railway, which Iarnród Éireann says helped minimise disruption to existing rail services. The line stayed open throughout.
Iarnród Éireann reports these completed quantities:
- 7.5 km of new track, alongside repositioning the existing single track.
- More than 94,000 tonnes of earth moved and more than 8,750 tonnes of rock removed.
- 20 retaining walls constructed along the track.
- More than 10 km of drainage installed.
- More than 83,000 tonnes of track formation laid.
Track laying is now largely complete, but Iarnród Éireann does not present the corridor as finished. The company says overall completion in 2027 will move in line with completion of the re-signalling of the full Cork rail network.
What does Phase 1 have to finish?
Phase 1 of the Cork Area Commuter Rail Programme incorporates the new €23 million platform 6 at Kent Station, the Glounthaune to Midleton twin-track and Cork area signalling and communications upgrade projects.
The stated budgets make Kent’s platform the smaller ticket: €23 million for platform 6 against €90 million for the Midleton track.
Iarnród Éireann says Phase 1 will deliver the capacity required for “a significant increase in train service frequency” on each of Cork’s three commuter lines, to Cobh, Midleton and Mallow. The company says Phase 1 will be fully complete in 2027.
What does Phase 2 add?
Iarnród Éireann says Phase 2 will provide eight new stations, a new depot, electrification of the network and a new fleet. Together, those works will ultimately support up to 10-minute rail service frequency on each of Cork’s three commuter lines.
The company held the second public consultation on Phase 2 in May 2026. Iarnród Éireann expects lodgement of a Railway Order Application to An Coimisiún Pleanála at the end of 2026. The application is the next stated milestone.
Iarnród Éireann also says critical-infrastructure designation will allow it to accelerate delivery of the wider package. It describes the aim as “a high-capacity, high-frequency and more sustainable rail network” for Cork. The timetable is still the test.
The next hard checkpoint is the expected Railway Order Application at the end of 2026. Phase 2’s eight stations, depot, electrification, new fleet and 10-minute service ambition remain tied to that larger programme, while the Glounthaune to Midleton work targets completion in 2027.
Source: premierconstructionnews.com