Helix Construct collapse leaves suppliers with nearly £5m unpaid
Helix Construct went into administration in September with nearly £5m of subcontractor and supplier invoices unpaid, £2.3m owed to lenders and £260,000 missing from 35 staff pay.
- Section
- Construction
- Author
- By Grace Kim
- Filed
- Length
- 3 min read
Key takeaways
- Helix Construct entered administration in September, leaving nearly £5m (£4.8m) unpaid to hundreds of subcontractors and suppliers.
- The Newbury-based firm also owed £2.3m to banks and financiers and £260,000 in outstanding pay to 35 staff.
- Turnover for the 18 months to June 2025 reached £40m, against £21m in the previous 12-month financial year.
- Administrator KR8 Advisory Limited filed the debt update at Companies House.
- Auditors raised concerns over the valuation and profit recognition on several contracts.
By Grace Kim
Helix Construct went into administration in September leaving hundreds of subcontractors and suppliers with nearly £5m of unpaid invoices, according to a Companies House update filed by administrator KR8 Advisory Limited.
The Newbury-based firm had traded since 2017, specialising in design and build construction for affordable housing, education, care and commercial projects across London and the south of England.
What did Helix Construct leave unpaid?
KR8 Advisory Limited's update breaks the estate's debts into three lines:
- Nearly £5m (£4.8m) owed to hundreds of subcontractors and suppliers.
- £2.3m owed to banks and financiers.
- £260,000 in outstanding pay for 35 staff.
So the collapse lands on three groups at once: the trade creditors who did the work, the lenders who funded it, and the employees who built it.
Was the business thriving before it failed?
Turnover says yes. For the 18 months to June 2025, turnover reached £40m, against £21m in the previous 12-month financial year.
The two periods differ in length, so the comparison covers more trading rather than a clean step change. The latest accounts also record growing cash and profitability pressure.
Auditors raised concerns over "valuation and profit recognition on several contracts". That flag sits closest to the cash. A query over contract valuation and profit recognition means the reported £40m cannot be read as money already sitting in the estate.
Two questions sit inside that phrase. One asks whether the work booked on a contract is worth what the contract says it is worth. The other asks how much of that value may be recorded as profit at all. Auditors flagged both, on several contracts.
What does design and build mean for the risk?
It puts design and construction in one pair of hands, and any argument over what was owed and how much profit to book runs through both. That concentration is the context in which the auditors' concerns matter so much to unpaid creditors.
What does this change for suppliers?
It gives them something the collapse date alone does not: a filed, official account of what Helix Construct owed, and to whom. Administration puts an administrator in control of a failed company's finances, and KR8 Advisory Limited's update is the first public snapshot of what the estate holds and what it owes.
Recovery for the 35 staff still owed £260,000 and the hundreds of trade creditors owed nearly £5m now depends on what the administrator can raise and distribute. For the lenders, £2.3m of financing sits exposed to the same outcome.
The scale of the shortfall is the scale of the supply chain that carried the building work: the firms supplying labour, materials and plant for each job, many of them now unpaid for work already delivered.
The next documents to watch are the administration's progress reports on the estate, which will set out what has been collected and what can be distributed to creditors. Neither the size of the turnover nor the length of the trading history answers the question every unpaid supplier is asking. Helix Construct's £40m turnover shows how far the firm scaled in eight years of trading; the contract valuations its auditors questioned will decide how much of that scale reaches the people who built it.
Source: Construction Enquirer