DEPDev ‘very concerned’ over flagship project delays
DEPDev ‘very concerned’ over flagship project delayspixel2013 / pixabay

Construction

33 of 37 Philippine Flagship Projects Miss Schedule, DEPDev Warns

DEPDev says 33 of 37 flagship projects due by 2028 are behind schedule, risking cost overruns on a P1.45-trillion pipeline including the P735.63-billion New Manila International Airport.

Author
By Marcus Bennett
Filed
Length
3 min read

Key takeaways

  • 33 of 37 flagship projects due 2026-2028 are behind schedule as of September, per DEPDev data.
  • The 37 projects carry a combined indicative cost of P1.45 trillion.
  • The P735.63-billion New Manila International Airport is among delayed 2028 completions.
  • The full IFP portfolio spans 201 projects worth P10.25 trillion.
  • The proposed 2027 budget allocates P44.5 billion to 18 IFPs due by 2028.

Thirty-three of the 37 Philippine infrastructure flagship projects targeted for completion between 2026 and 2028 are behind schedule as of September, according to Department of Economy, Planning, and Development (DEPDev) data. Only four remain on track. The 37 projects carry a combined indicative cost of P1.45 trillion.

DEPDev Secretary Arsenio M. Balisacan did not soften the assessment. "We are very concerned. That is why we are focusing on the monitoring of those projects and especially the availability of funding," he told reporters on the sidelines of the 64th Philippine Economic Society Annual Meeting and Conference on Nov. 20.

What does the delay cost?

For practitioners, Balisacan framed the damage in two parts. First, deferred benefits. "Number one, you forego the benefits that they would have brought," he said. "If you delay that, the benefits will be reduced. Because the benefits are far into the future, if you discount to the present, it's already low."

Second, price escalation. "Number two, it becomes more costly to complete the project because the project proponents or implementers would come back to us to ask for adjustment in the cost because of the impact of changes in prices," he added. Railways and highways, he noted, become much more expensive when delayed.

Which projects are slipping?

All six projects due for completion this year are behind schedule, along with nine of the 12 due in 2027 and 18 of the 19 due in 2028. The 2028 laggards include:

  • the P735.63-billion New Manila International Airport
  • the P77-billion Metro Rail Transit Line 7 Project
  • the P70.81-billion Davao City Bypass Construction Project
  • the P28.78-billion Cebu Bus Rapid Transit Project

The pipeline itself has shrunk. Projects targeted for completion by 2028 fell to 37 in the third quarter of 2026 from 60 in the second quarter of 2025, DEPDev data showed, reflecting completions, revised schedules and changes to the project list. Nineteen projects have been rescheduled beyond 2028.

What is blocking delivery?

Right-of-way and site problems dominate. Among the 37 projects due by 2028, seven reported issues involving site conditions or availability, including right-of-way concerns; three faced procurement issues; and two had budget and funds flow concerns.

The full portfolio tells the same story at larger scale. The government's infrastructure flagship project (IFP) portfolio now comprises 201 projects with an indicative total cost of P10.25 trillion. Eight were completed from 2023 to 2025, while 156 are targeted for completion beyond 2028. Across the portfolio, site issues affect 21 projects, procurement issues affect 12, and design, scope or technical issues and budget and funds flow concerns each affect eight.

What is DEPDev prescribing?

DEPDev identified aligning budget programming with project completion schedules as a key action, giving priority to projects at advanced stages of readiness with confirmed delivery timelines. It also called for updated completion action plans for delayed projects, with clear milestones and accountability, and stronger coordination to resolve right-of-way and permitting constraints.

Funding for the near-term pipeline is set: under the proposed 2027 national budget, P44.5 billion is allocated to 18 IFPs targeted for completion by 2028, according to DEPDev. Whether that allocation holds depends on implementers hitting milestones the monitoring system will now track project by project.

Source: bworldonline.com

philippine-infrastructure flagship-projects project-delays public-funding depdev

Share this article:

More from Marcus Bennett

Marcus Bennett

Show full bio

Correspondent covering money, funding and market shifts around construction industry, architecture, interior design at Built Current.

343 articles

More projects

« Previous articleNext article »