DOB details fatal Brooklyn jobsite’s scope of work, past violations
DOB details fatal Brooklyn jobsite’s scope of work, past violationsAI-generated

Construction

DOB Expands Safety Sweep to More Than 160 Sites After Collapse

After eight deaths in a Flatbush building collapse, New York’s Department of Buildings expanded a safety sweep to more than 160 sites and detailed prior stop-work violations.

Author
By Grace Kim
Filed
Length
2 min read

Key takeaways

  • Eight people died in the Nov. 11 collapse, including two construction workers.
  • DOB expanded its sweep from five to six entities at more than 160 sites.
  • The planned project had nine stories, 64 dwelling units and approved sub-grade work on a three-story building.
  • DOB fines totaled $2,500 in March and $10,000 in April; both were paid.
  • The Nov. 11 cause remains undetermined, and the city will hire an outside engineering firm for an independent report.

By Grace Kim

Eight people, including two construction workers, died in the Nov. 11 building collapse in Flatbush, Brooklyn, which the New York City Department of Buildings is investigating. Crews are removing debris and working on shoring, according to the DOB.

Following an announcement last week by New York City Mayor Zohran Mamdani, the DOB expanded its safety sweep from five to six entities at more than 160 sites around the city. The agency shared the expansion with Construction Dive by email.

What does the expanded sweep change for workers?

It broadens the DOB’s search for hazards at more than 160 sites, according to the agency. Inspectors are looking for “any site safety issue that endangers the public or workers.”

The DOB says it will not identify the six entities. It is withholding their identities “to protect the integrity of the sweep.” The restriction limits what the public can learn about who is under review.

The wider review does not resolve the cause of the Flatbush collapse. For the forensic investigation, the city will hire an outside engineering firm to produce an independent report. The DOB describes that approach as standard practice for major buildings-related incidents.

The approved scope of work

The project team had planned a nine-story mixed-use building with 64 dwelling units, according to the DOB. The three-story building had approval for sub-grade work involving earthwork, foundation work and support of excavation.

The team filed an application for the larger structure, but the DOB returned it with objections, the agency said. Permits reviewed by Construction Dive list Robert Fischman of W6 Facility X as the owner. They also name Cheng-Yi Lin Architecture as the architect of record.

Neither Fischman nor Cheng-Yi Lin Architecture could be reached for comment.

Violations before the collapse

The DOB said the Flatbush jobsite had previously violated a stop-work order. Its enforcement record lists two penalties:

  • March: The DOB issued a $2,500 penalty for inadequate demolition protections for neighboring properties.
  • April: The DOB issued a $10,000 penalty for violating the stop-work order associated with the first penalty.

Both fines have been paid, according to the agency.

The investigation ahead

The DOB said it remains too early to determine what caused the collapse. Its next two steps are the outside engineering report and the findings from the six-entity safety sweep.

The report will address the cause at the Flatbush site. The sweep will identify the site-safety issues the DOB finds across more than 160 locations. Until that work is complete, the agency has not established why the building failed.

Source: Construction Dive

flatbush-building-collapse construction-site-safety dob-safety-sweep new-york-city-department-of-buildings

Share this article:

More from Grace Kim

Grace Kim

Show full bio

Staff writer covering money, funding and market shifts around construction industry, architecture, interior design at Built Current.

345 articles

More projects

« Previous articleNext article »