South Wales highways framework rises £135m to £405m
The SWTRA Highways & Structures Framework 2027 has risen 50% to £405m, with two lots covering roads, bridges, resurfacing and maintenance across South Wales.
- Section
- Construction
- Author
- By Priya Raman
- Filed
- Length
- 2 min read
Key takeaways
- Forecast value increased by £135m to £405m from £270m.
- The uplift is 50%; two lots are worth £252m and £153m.
- Up to eight contractors will share the framework.
- Initial term: four years from April 2027, extendable by two years to March 2033.
- Tenders close at noon on 18 December; awards are expected on 8 March 2027.
By Priya Raman
The SWTRA Highways & Structures Framework 2027 now carries a forecast value of £405m, £135m above its original £270m advertisement, according to the procurement led by Neath Port Talbot County Borough Council. The uplift equals 50%, and councils have opened the formal competition for contractors to deliver road and bridge work across South Wales. Its procurement partners are Carmarthenshire and Monmouthshire councils.
The framework (a multi-supplier purchasing route) covers civil engineering (construction and maintenance of infrastructure), structural renewals, bridge strengthening, carriageway maintenance (repair of the road's running surface) and road resurfacing. Up to eight contractors will share it across South Wales's strategic road network (major routes carrying regional traffic).
The published scope divides the programme into two lots (separately priced work packages):
- Largest lot, £252m: Highways and structures, including bridge repairs, tunnel works, safety improvements, lighting and intelligent transport systems (traffic-management technology).
- Second lot, £153m: Resurfacing, drainage, pavement (road-surface) improvements, kerbing (road-edge restraints), road markings and emergency maintenance.
Together, the two lot values match the full £405m forecast. The first package covers structures and associated infrastructure. The second concentrates on surfacing, drainage, kerbs, markings and urgent maintenance.
The framework will initially run for four years from April 2027. The councils hold an option to extend it for another two years, to March 2033. The councils expect award decisions before that initial term begins.
The framework will primarily serve the South Wales strategic road network across Cardiff and the Vale of Glamorgan, Swansea, Bridgend, Neath Port Talbot, Carmarthenshire, Monmouthshire, Newport and the Gwent valleys.
Contractors have until noon on 18 December to submit tenders. The councils expect award decisions on 8 March 2027.
What does the £405m framework change for contractors?
The uplift expands the forecast pipeline by half, from £270m to £405m, and divides the opportunity into two defined packages. Up to eight contractors can share the arrangement. The £252m package covers highways and structures; the £153m package covers resurfacing and maintenance.
For contractors, the practical change is scale and timing: they must prepare bids by noon on 18 December for access to a pipeline that has risen by £135m and spans bridges, tunnels, resurfacing, drainage, lighting, structural renewals and emergency maintenance.
For councils, the larger forecast means more road and bridge packages to manage once awards begin. The initial term provides a defined delivery window from April 2027. The extension can carry the framework to March 2033 if exercised.
The next test is contractor participation at the 18 December tender deadline. The councils expect awards on 8 March 2027, ahead of the initial four-year term from April 2027. The extension to March 2033 remains optional.
Original: etenderwales.ukp.app.jaggaer.com
More from Priya Raman
Show full bio
News editor covering people, launches and day-to-day practice in construction industry, architecture, interior design at Built Current.
306 articles