Shrewsbury railway bridge maintenance work to continue until JanuaryTien-seven / pixabay

Renovation & Retrofit

Network Rail Extends Shrewsbury Bridge Repairs Into January 2027

Shrewsbury's Castle Foregate and Great Western Railway bridge repairs will now run until January 2027 after engineers uncovered further steelwork defects during the scheme.

Author
By Amara Osei
Filed
Length
2 min read

Key takeaways

  • Bridge maintenance in Shrewsbury extended from this month to January 2027
  • Overnight work runs 12.30am-7am on Sundays until end of November 2026
  • December 2026 closures planned 8pm-6am on Sunday nights into Monday mornings
  • Scaffold removal anticipated in early January 2027
  • Contractor AmcoGiffen found additional steelwork defects requiring remedial works

Repairs to two railway bridges in Shrewsbury will now run until January 2027, after engineers found further steelwork defects that Network Rail says must be fixed before the scheme can close. The work on the Castle Foregate and Great Western Railway bridges was due to finish this month.

Network Rail's contractor, AmcoGiffen, is carrying out cleaning, repairs and repainting of the bridge structures, essential steelwork repairs, and the installation of new pigeon-proofing mesh beneath the bridges. Further investigations during the ongoing repairs identified additional steelwork defects requiring remedial works, which Network Rail says are necessary to ensure the long-term structural integrity of the bridges.

The result: a programme extension measured in months, not weeks.

Will the roads stay open?

Mostly. The bridges will remain open to vehicular traffic during daytime hours. However, temporary road closures will continue on Castle Foregate, Cross Street and Howard Street so the contractor can safely undertake the additional steelwork repairs and complete the remaining phases of the project.

Some parts of the bridge structure can only be accessed when no trains are running. Because further steelwork repairs have been identified in precisely those areas, work will continue between 12.30am and 7am on Sunday mornings. The associated road closures will remain in place on Saturday nights until the end of November 2026.

These overnight closures will allow:

  • Completion of the additional steelwork repairs identified during the works
  • Installation and final adjustments to the new pigeon-proofing mesh
  • Preparatory works for the subsequent removal of the scaffold structure

What happens in December?

More night work. Further activities are programmed throughout December 2026, including the completion of outstanding repair work and associated project activities. Temporary overnight road closures will apply on Sunday nights into Monday mornings, between 8pm and 6am, throughout the month.

The scaffolding will remain in place during this period, though the existing arrangement will be amended to allow pedestrian access beneath the structure. A small mercy for anyone walking through central Shrewsbury in winter.

When will the scaffolding finally come down?

The final phase involves dismantling and removing the remaining scaffold structure. This work is currently anticipated to take place in early January 2027 and will require additional overnight road closures.

So a project that was meant to wrap this month now stretches across three calendar years of night shifts, weekend closures and pigeon-proofing. Shrewsbury's drivers get daytime access throughout; its Sunday-morning commuters and December night-trippers bear the disruption. Network Rail's argument is straightforward — the defects were found during the works, and fixing them now protects the bridges' long-term structural integrity rather than deferring the problem to a costlier future repair.

Source: shropshirelive.com

bridge-repairs network-rail shrewsbury structural-steelwork railway-infrastructure

Share this article:

More from Amara Osei

Amara Osei

Show full bio

Market editor covering companies, deals and strategy in construction industry, architecture, interior design at Built Current.

354 articles

More projects

« Previous articleNext article »