Jacobs, WSP and Millstone Weber win $583 million I-70 contract
Missouri DOT says a $583 million contract covers 44 miles of I-70 from Kingdom City to Warrenton, with a third lane each way, new concrete pavement and bridge work; construction starts in 2027.
- Section
- Construction
- Author
- By Priya Raman
- Filed
- Length
- 3 min read
Key takeaways
- $583 million and 44 miles define the Kingdom City-to-Warrenton I-70 contract.
- The project adds a third lane in each direction and replaces all existing pavement with full-depth concrete.
- The scope includes three bridge replacements, six bridge rehabilitations and a fourth eastbound climbing lane at Mineola Hill.
- This is the sixth project in a nearly 200-mile I-70 program; Missouri’s fiscal year 2024 budget included $2.8 billion for third lanes.
- Construction starts in the first half of 2027; Missouri DOT expects completion in late 2030.
By Priya Raman
A $583 million contract will fund 44 miles of Interstate 70 improvements between Kingdom City and Warrenton, Missouri, after the Missouri Highways and Transportation Commission (MHTC) selected a three-firm joint venture.
The six-member MHTC board leads Missouri DOT, which announced the award on Nov. 5. According to Missouri DOT, the joint venture (three firms working together) comprises contractor Millstone Weber, designer Jacobs and key partner WSP. It will spearhead the design-build project (a delivery method that combines design and construction under one team).
“With this award, six out of eight expansion projects are now moving forward in this historic $2.8 billion investment – an investment that will benefit Missouri’s growing communities well into the future,” said Warren Erdman, MHTC chairman, in Missouri DOT’s announcement.
Scope of the 44-mile project
According to Missouri DOT, the team will add a third lane in each direction along the 44-mile route. The work also replaces all existing I-70 pavement between Kingdom City and Warrenton with new full-depth concrete pavement (concrete through the full depth of the pavement section).
Missouri DOT listed these additional scope elements:
- Replace three bridges.
- Rehabilitate (repair) six bridges.
- Add a fourth eastbound climbing lane (an uphill traffic lane) at Mineola Hill.
- Redesign the Norfolk Southern Railroad Crossing at High Hill.
Missouri DOT’s scope accounts for nine bridge structures: three replacements and six rehabilitations.
Missouri’s wider I-70 program
The Kingdom City-Warrenton award is the sixth project in a series intended to improve nearly 200 miles of I-70 from Blue Springs to Wentzville, according to Missouri DOT’s Nov. 5 announcement.
Missouri DOT’s announcement says the state’s fiscal year 2024 budget included $2.8 billion to build a third lane for I-70 across the state. One project on an I-70 segment, the St. Louis Airport Corridor job in St. Louis County, received $42.1 million in federal DOT funding last month.
Missouri DOT described I-70 as a major thoroughfare for the Cave State. The route connects St. Louis with Kansas City. It carries more rural daily traffic than any other route in Missouri, according to the state agency.
Delivery method and schedule
Missouri DOT’s announcement calls the award a win for proponents of design-build in the state. Missouri recently passed legislation expanding the availability of progressive design-build (a staged version of design-build) to all state agencies.
Missouri DOT said the team is negotiating final details of the contract. The agency’s schedule calls for construction to begin in the first half of 2027. Missouri DOT anticipates completion in late 2030.
What does this change for drivers?
Under Missouri DOT’s published scope, drivers between Kingdom City and Warrenton would have three lanes in each direction once work finishes. They would also have new concrete pavement, three replacement bridges, six rehabilitated bridges and a fourth eastbound climbing lane at Mineola Hill. The practical change is a rebuilt 44-mile corridor with those improvements, targeted for late 2030 if contract negotiations conclude and construction starts in the first half of 2027.
Source: Construction Dive