BAM will spend 12 months testing Middlesbrough's 1911 Transporter Bridge, closed for seven years, before pricing a restoration the council has yet to fund.

Author
By Elena Vasquez
Filed
Length
2 min read

Key takeaways

  • BAM appointed to the Transporter Bridge rescue under an early contractor involvement agreement with AtkinsRéalis
  • The Grade II* listed Middlesbrough crossing has been closed for seven years over structural and safety concerns
  • 12 months of detailed testing and trials will precede refurbishment proposals and cost estimates
  • The bridge opened in 1911 and uses a suspended gondola to ferry vehicles and pedestrians across the River Tees
  • Middlesbrough Council has not yet established the full restoration cost or secured funding

BAM has been appointed to lead the rescue of Middlesbrough's Transporter Bridge, a Grade II* listed crossing that has stood closed for seven years over structural and safety concerns. The contractor will spend the next 12 months carrying out detailed testing and trials on the landmark before drawing up refurbishment proposals and cost estimates for the River Tees crossing.

BAM will work alongside engineering consultant AtkinsRéalis under an early contractor involvement agreement. That structure matters here. Instead of designing a scheme first and tendering the build later, the council is bringing the contractor in at the investigation stage, so the people who will price and deliver the work help shape what the work actually is.

What is being rescued?

The bridge opened in 1911 and links Middlesbrough with Port Clarence. It carries traffic in an unusual way: a suspended gondola ferries vehicles and pedestrians across the River Tees rather than running a road deck the full span. Few structures of this type survive anywhere, which is part of why the crossing carries its Grade II* listing, a protection reserved for buildings and structures of particular importance, more than special interest.

The bridge has now been out of service for seven years, roughly a fifth of its entire life to date. Middlesbrough Mayor Chris Cooke framed the appointment as the moment the project moves from background work to concrete proposals.

He said: "Lots of work has already been done, and the appointment of BAM allows us to explore detailed proposals to restore the Transporter to its former glory. We want it to be used and enjoyed by future generations."

What happens in the next 12 months?

The year ahead is diagnostic. BAM's testing and trials will establish the condition of the 114-year-old structure in enough detail to support two things the project currently lacks:

  • Refurbishment proposals for the crossing
  • Reliable cost estimates for carrying out the works

Only once those numbers exist can the council begin the harder conversation about money.

Who pays for it?

That question remains open. The council has yet to establish the full restoration cost, and it has not secured the funding needed to carry out the works. The appointment of BAM and AtkinsRéalis therefore covers investigation and proposals, not construction. For a heritage structure of this scale, the final bill is likely to shape the pace of everything that follows, from funding applications to a reopening date.

The next hard milestone comes when the 12-month testing programme ends and a costed proposal lands on the Mayor's desk.

Source: Construction Enquirer

transporter-bridge middlesbrough heritage-restoration structural-assessment bam

Share this article:

More from Elena Vasquez

Elena Vasquez

Show full bio

Senior reporter covering money, funding and market shifts around construction industry, architecture, interior design at Built Current.

354 articles

More projects

« Previous articleNext article »