AI power rush sends data centers hunting for used turbines and jet engines
AI power rush sends data centers hunting for used turbines and jet enginesTama66 / pixabay

Construction Tech

AI Data Centers Spur Demand for Secondhand Gas Turbines

AI data centers are driving gas-turbine orders beyond 100 GW. With US deliveries averaging six years, developers are buying used, refurbished and jet-derived units.

Author
By Elena Vasquez
Filed
Length
5 min read

Key takeaways

  • Worldwide gas-turbine orders exceed 100 GW, above estimated production capacity of 60 GW to 70 GW.
  • US gas-turbine deliveries now average six years; delivery discussions focus on 2030–2031.
  • US data centers account for nearly 17 GW of demand this year, a figure that can more than triple by 2028.
  • Crusoe ordered 13 aeroderivative turbines totaling 650 MW from ProEnergy in April.
  • Used turbines cost $1.5 million to $1.7 million per MW; refurbished units cost about $1.3 million, against $2 million to $2.5 million for new units.

By Elena Vasquez

Worldwide gas-turbine orders have topped 100 GW, against estimated production capacity of 60 GW to 70 GW, according to Wood Mackenzie.

AI data centers have become major buyers in a market that, until a few years ago, served almost only traditional utilities. Siemens Energy, GE Vernova and Mitsubishi Heavy Industries dominate that market, and all three say the AI boom has driven orders beyond their production capacity.

Wood Mackenzie expects global manufacturing capacity to reach around 87 GW in 2028. Jefferies expects 129 GW of turbine power demand then, while estimating that US data centers account for nearly 17 GW of demand this year. That US figure can more than triple by 2028.

Despite growing skepticism about AI technology and a recent sell-off in related stocks, the equipment surge continues. More than a dozen brokers, service firms and suppliers told Reuters that utilities, developers and firms are scouring the world for secondhand gas turbines.

They are reviving mothballed machines and converting retired jet engines rather than wait for new-equipment backlogs to clear. Ana Amicarella, chief executive officer of equipment-services provider EthosEnergy, said: “That secondary market is very, very hot right now.” She added: “We also have seen an escalation on the prices of what people are demanding.”

Why are buyers turning to used equipment?

Aurora Tenorio, a senior analyst at energy consultancy Wood Mackenzie, said of the US turbine market: “Delivery conversations (are) firmly focused on the 2030 to 2031 window.” She put average US gas-turbine delivery time at six years.

The wait leaves buyers exposed to price increases as well as delay. Origin Partners buys power equipment for data-center developers and supplies the used and refurbished figures. Aurora Energy Research provides the new-turbine estimate.

Can the used market close the gap?

Noor Qureshi, an associate at Enverus Intelligence Research, said the answer is only partial. “The market is already constrained, with limited excess supply, so it is unlikely to offset a meaningful share of the delays,” she said. Qureshi also identified air permits and grid access as other causes of delay.

No reliable estimate shows how much the secondary market contributes to the global turbine supply, worth about $25 billion a year. Its emergence nevertheless reflects the data-center boom’s reach into other industries.

AI infrastructure firm Crusoe ordered 13 aeroderivative gas turbines from US-based ProEnergy in April. The units use jet engines made by GE Aerospace and have a combined capacity of 650 MW for Crusoe’s US AI data center projects.

Crusoe described the order as a strategic move to scale fast. ProEnergy and Crusoe did not respond to requests for information.

What are the risks of older equipment?

Overhauled turbines can have unclear maintenance histories, limited remaining life and weak long-term servicing, Tenorio said. She also said converted jet engines raise questions about their fitness for continuous work as power generators. Years-long delivery waits sustain demand despite those drawbacks.

“Every few weeks we get a request to say, ‘Can you find a used gas turbine to put into a data center?’” said Darayus Pardivala, who leads the US aftermarket business of Sulzer. Pardivala would not disclose details about the clients or the centers’ locations.

How much do used turbines cost?

Secondary equipment carries lower purchase prices than new turbines. Origin Partners buys power equipment for data-center developers and supplies the used and refurbished figures. Aurora Energy Research provides the new-turbine estimate.

  • Well-maintained used turbines cost about $1.5 million to $1.7 million per MW, according to Zach Machuca, managing partner at Origin Partners.
  • Refurbished turbines cost about $1.3 million per MW, Machuca said.
  • New turbines cost about $2 million to $2.5 million per MW, according to Aurora Energy Research.
  • The discount can be greater for smaller, cheaper units.

Dan Poole, general manager at ReflowX, which connects buyers with turbine owners, said two 14.5-MW turbines made by Solar Turbines, a Caterpillar unit, recently sold for $12.5 million, or around $430,000 per MW. Poole said new ones would cost about $35 million and take five years to deliver; he did not disclose the buyer.

Developers turn to small turbines when larger units remain hard to source. According to Scott Schreeg, director of sales at US equipment supplier SVI Bremco, they sometimes deploy more than 100 at one site and mix models and brands.

Where is the demand spreading?

The Tennessee Valley Authority, a federally owned US utility, said prices for all equipment—new, used or refurbished—have “increased significantly” over the past two years. Jim Matheson, CEO of the National Rural Electric Cooperative Association, said its members face unprecedented lead times and surging prices.

“Co-ops that need new capacity are turning to every viable option,” Matheson said, including purchasing refurbished turbines. His association groups nonprofit utilities owned by their customers.

Finland’s Wartsila has booked around 3 GW of orders since spring last year from US data centers for power units running on gas engines instead of turbines. Anders Lindberg, president of the group’s energy business, said: “What’s driving the market? Lead times, lead times, lead times.”

Qureshi’s assessment leaves little room for the secondary market to solve the supply problem. It can cover some orders, but not a meaningful share of delays, while air permits, grid access and manufacturing gaps persist. Developers will likely keep using smaller gas engines, refurbished turbines and mixed-brand installations to meet project schedules on a compressed timetable.

Source: bworldonline.com

ai-data-centers gas-turbines power-generation refurbished-equipment equipment-lead-times

Share this article:

More from Elena Vasquez

Elena Vasquez

Show full bio

Senior reporter covering money, funding and market shifts around construction industry, architecture, interior design at Built Current.

354 articles

More projects

« Previous articleNext article »