$16B Hudson Tunnel project launches second tunnel boring machine
The Gateway Development Commission says both Hudson Tunnel rail tubes are under construction. Two machines will excavate 5,100 feet each before a second pair starts beneath the Hudson River in 2028.
- Section
- Construction
- Author
- By Elena Vasquez
- Filed
- Length
- 3 min read
Key takeaways
- The $16 billion Hudson Tunnel project now has both new rail tubes officially in progress.
- The second tunnel boring machine began the southern tube last week; the first began the northern tube in October.
- The first machine has bored about 400 feet and installed more than 60 rings of tunnel lining.
- Each machine will excavate 5,100 feet through the Palisades before the river section starts in 2028.
- Crews have dug 50 to 60 feet at the access shaft; breakthrough is expected around this time next year.
Construction of both new rail tubes in the $16 billion Hudson Tunnel project is officially under way, the Gateway Development Commission (GDC) confirmed at a Wednesday board meeting. Jim Starace, GDC chief of program delivery, said crews launched the second tunnel boring machine last week.
The machine has started excavating the southern tube, according to Starace. A Wednesday GDC release said the first machine, which began work in the northern tube in October, had bored about 400 feet and installed more than 60 rings of tunnel lining.
GDC CEO Tom Prendergast said, “The start of the tunnel boring this fall was our major milestone, but it was only the beginning,” during the board meeting. He added, “We recently launched our second tunnel boring machine, and we now have officially started building both of the new tunnels’ tubes in the Palisades.”
What does the Palisades Tunnel package include?
According to GDC, the two machines will excavate the first 5,100 feet of each tube. The route runs from the tunnel portal in North Bergen, New Jersey, to the Hudson County Access Shaft on the border of Weehawken and Hoboken. Each 5,100-foot drive covers just under one mile.
According to GDC, a joint venture of Schiavone Construction, Lane Construction and Dragados leads the Palisades Tunnel package, which includes the excavation and the access shaft. The Port Authority of New York and New Jersey manages delivery of the package in partnership with GDC.
How does each machine build the tunnel?
Starace said each machine cuts through hard rock and installs the permanent lining as it advances. Inside the machine’s shield, a small crane lifts precast concrete segments into place, and workers bolt them together. His account places excavation and lining in the same operating cycle, which links the machine’s advance rate directly to the lining work.
Starace said, “The second one is really just beginning. The production rate is increasing as the work continues and as the operation continues,” during the meeting. He added, “So, as the production of the TBM continues, we expect a continued increase in production until we come out on the other side in Weehawken.”
At the other end of the Palisades section, crews have dug about 50 feet to 60 feet down at the access shaft and reached rock, Starace said. He expects the shaft to be complete and the machines to break through around this time next year.
When does work move beneath the Hudson River?
Each 5,100-foot drive forms the Palisades leg rather than the full river crossing. After the breakthrough, crews will remove the machines and bring in a second pair designed for the ground beneath the Hudson River. Starace said boring on that section is slated to begin in 2028.
The next near-term milestone is the completed shaft and breakthrough around this time next year. The 2028 river start follows completion of the Palisades drive, removal of both machines and arrival of the second pair, according to the GDC sequence.
Source: Construction Dive