Two Japanese Bidders Push NSCR Rail Contract Deadline to Jan. 14
DoTr moved the NSCR O&M bid deadline to Jan. 14 at the request of two Japanese bidders. The 15-year contract covers a 147-km line with a P114.65 billion net worth requirement.
- Section
- Construction
- Author
- By Elena Vasquez
- Filed
- Length
- 3 min read
Key takeaways
- Bid deadline for the NSCR O&M contract moved to January 14 at the request of two Japanese bidders.
- The 15-year contract covers a 147-km railway with full operations targeted by January 2032.
- Bidders need a minimum net worth of P114.65 billion as of the 2024 financial year.
- About 10 foreign and local firms expressed interest; 74 firms are interested in the MRT-3 O&M deal.
- MRT-3 contract award is targeted for June-July 2027, with takeover by October 2027.
The Philippine Department of Transportation (DoTr) has pushed the bid submission deadline for the North-South Commuter Railway (NSCR) operations and maintenance contract to January 14 next year, after two Japanese bidders asked for more time.
"Two Japanese bidders requested an extension until Jan. 14," Transportation Secretary Vivencio B. Dizon told reporters on the sidelines of an event last week. He declined to name the companies, saying only that they are Japanese.
Why the delay?
This is the third deadline the tender has slipped through. Transportation Undersecretary for Railways Timothy John R. Batan said bid submissions were originally set for late July, then moved to September, while the DoTr continued holding one-on-one sessions with prospective bidders. About 10 foreign and local companies expressed interest in the contract as of July.
The field of contenders reads like a who's-who of global rail. The DoTr is in discussions with Japanese operators Tokyo Metro Co., Ltd., plus JR East and JR West — the companies that run Japan's Shinkansen high-speed network. France's RATP Group, which oversees the Paris Metro, attended the DoTr's pre-bidding conference last year. Fellow French firms Keolis SA, a transportation and mobility networks company, and rolling stock manufacturer Alstom also signified interest. On the domestic side, San Miguel Corp. and the Lopez group's construction company First Balfour, Inc. attended the pre-bid conference.
What does the winner get?
The contract covers 15 years of running a 147-kilometer railway that will connect Malolos, Bulacan with Clark International Airport, and Tutuban, Manila with Calamba, Laguna. For scale, the line will eventually tie together airport service and three major urban corridors in a single system.
The qualification bar is high. According to instructions published in October last year, bidders must show a minimum net worth of P114.65 billion — or its foreign-currency equivalent — as of the 2024 financial year. That figure alone signals the DoTr wants deep-pocketed, experienced operators.
Experience requirements are just as strict. At least one consortium member or affiliate needs 10 years running a rail line that moves at least 45,000 passengers per hour in each direction. Another entity must have eight years maintaining railway infrastructure and systems, including use of a computerized maintenance management system. A third needs eight years in track and civil infrastructure maintenance.
When will the trains actually run?
The NSCR is expected to be fully operational by January 2032, but segments will open earlier: Malolos to Valenzuela could start running by December 2027, and Clark to West Valenzuela by October 2028.
After the NSCR, the DoTr plans to auction O&M contracts for Metro Rail Transit Line 3 (MRT-3), then Light Rail Transit Line 2 and the Metro Manila Subway. "Next year is our target (for these) rail projects," Dizon said. About 74 domestic and foreign firms have expressed interest in the MRT-3 deal since May, with solicited bidding possibly beginning by October and submissions expected by March 2027. Award is targeted between June and July 2027, and the winning bidder would take over MRT-3 operations by October 2027 — a pipeline that puts the Philippines' entire metro network under private-style concessions within the decade.
Source: bworldonline.com
More from Elena Vasquez
Show full bio
Senior reporter covering money, funding and market shifts around construction industry, architecture, interior design at Built Current.
400 articles