O'Hare Breaks Ground on $917M Concourse E with 24 New Gates
Chicago broke ground on the $917M Concourse E at O'Hare, adding 24 gates in two phases. An AECOM Hunt, Clayco and Bowa JV will build it alongside the $1.45B Concourse D.
- Section
- Construction
- Author
- By Grace Kim
- Filed
- Length
- 3 min read
Key takeaways
- The $917 million Concourse E project at O'Hare will add 24 gates across two phases.
- Phase one is worth $640 million and adds 14 gates plus 315,000 square feet of passenger space.
- A JV of AECOM Hunt, Clayco and Bowa also leads the $1.45 billion Concourse D with 19 gates.
- The $8.8 billion ORDNext program, the largest terminal expansion in O'Hare's history, is set to finish in 2034.
- The O'Hare Global Terminal, nearly doubling Terminal 2, is scheduled for completion in 2033.
Chicago has broken ground on a $917 million Concourse E at O'Hare International Airport, adding 24 gates to one of the country's busiest hubs. The Chicago Department of Aviation, alongside airline and project partners, announced the milestone Tuesday through Mayor Brandon Johnson's office.
The work splits into two phases. Phase one, worth $640 million, delivers 14 new gates and 315,000 square feet of passenger space. It also adds holdrooms and 21,000 square feet of concession space, per the announcement. Phase two, valued at $277 million, extends the concourse with 10 more gates — but only after the O'Hare Global Terminal wraps up in 2033. That terminal will nearly double the size of the airport's Terminal 2.
A joint venture of AECOM Hunt, Clayco and Bowa leads the construction team. The same JV already carries responsibility for the $1.45 billion Concourse D, which will add 19 gates. Concourse E will sit to the west of Concourse D, and the two will link through an underground passenger tunnel, according to the project page.
What does the new schedule change?
The team starts work under an updated timeline that lets both concourses proceed at the same time, rather than one after the other. According to the announcement, that concurrency is what gets the airport to the gate capacity it needs before the O'Hare Global Terminal can move forward.
"Passengers will experience these projects as one airport, and we have to manage them that way," said Dave Nisula, program manager for Connect Chicago Alliance, the CDA's Program Management Office, in the announcement. "Decisions about Concourse E have to account for the tunnel connections, the work underway on Concourse D and the future Global Terminal."
Together, the two concourses anchor a multibillion-dollar overhaul of O'Hare through its ORDNext program — the largest terminal expansion in the airport's history, per the ORDNext information page. Concourse D broke ground in 2025, and the full ORDNext program is scheduled to finish in 2034.
The scale of coordination is the real challenge. Zach Baughman, chief development officer and managing deputy commissioner of the CDA, told Construction Dive in September that the team had to balance construction on the $8.8 billion ORDNext program against the fact that O'Hare never stops operating.
"What makes or breaks the project is how well we've translated to our stakeholders what the impacts are going to be, how prepared they are to manage through those impacts, to have contingency plans when things go wrong, how well others in the department understand what the work is we're doing and how their day-to-day jobs are going to change because of that work," Baughman said in September.
With Concourse E now underway, O'Hare has three major pieces in motion at once — two concourses and the future Global Terminal. How well the JV and the CDA keep those overlapping schedules in sync will shape gate capacity at the airport well into the next decade.
Source: Construction Dive