Election Results Cloud Data Center Construction and Transportation Bill
Democrats flipped the House and Senate, and analysts expect data center project delays plus a probable slip for the surface transportation bill due Dec. 11.
- Section
- Construction
- Author
- By Marcus Bennett
- Filed
- Length
- 4 min read
Key takeaways
- Democrats flipped control of both the House and Senate in Tuesday's midterm elections
- Congress faces a Dec. 11 deadline on the surface transportation bill or the BUILD America 250 Act
- The Infrastructure Investment and Jobs Act raised average annual highway funding about 62% and transit funding about 67%
- New members of Congress are sworn in in January, when a transportation bill will likely be taken up
- Swearingen expects current transportation law to be extended with full funding into 2027
Democrats flipped control of both the House and the Senate on Tuesday night, and industry analysts now expect planned data center projects to face delays while a long-awaited federal surface transportation bill slips into next year.
Analysts called the result a "rebuke" of President Donald Trump's agenda. For construction practitioners, the blue wave changes two things: the permitting climate around data centers and the timeline for federal infrastructure money.
What does the election change for data center builders?
Daniel Fisher, senior vice president of government and external affairs at the Associated Equipment Distributors trade group, said Democrats in particular pushed for data center moratoriums at the state level, and he anticipates projects hitting more hurdles now that voters embraced that push.
"I'd expect many planned data center projects to be put off or delayed," Fisher told Construction Dive.
Still, Fisher said those changes minimally impact total demand for data center construction.
"However, at the end of the day, Democrats and Republicans must recognize the economic impact of data center construction and associated energy projects, and the importance to the country's ability to compete in the global AI race," Fisher said.
Michael Guckes, chief economist at ConstructConnect, said the widespread Democrat victory increases the likelihood of policy changes around data center projects — changes that could add costs, delays and uncertainty to an important construction growth source. Due to the size and scope of the boom to date, Guckes also expects strong demand to persist around these facilities.
"A change in Congressional control would not, by itself, imply a halt in data center construction," Guckes told Construction Dive. "[Policy changes] would not change the fact that data centers represent an important change to the future of how work will be done, nor does it change AI's importance to the future of national security."
Kristen Swearingen, vice president of government affairs at Associated Builders and Contractors, pointed to an immense opportunity in grid buildouts related to data centers and agreed momentum in the sector will persist.
"It heightens the prospect for moratorium discussions in states like Texas and Michigan, but it doesn't change what is coming either way," said Swearingen. "Many governors and their administrations, regardless of party, are seeking to lead on regulatory frameworks around data center construction that aim to address constituent concerns, while hopefully looking to maximize benefits from the boom for workers and the economy."
Do moratoriums actually stop projects?
Daren Shumate, founder of data center engineering firm Shumate Engineering and a former Fairfax County, Virginia, planning commissioner, argued temporary pauses help communities prepare for data center development. Moratoriums give local governments time to update zoning requirements to address concerns such as noise and water demand. Some rural areas, Shumate added, have never faced this type of industrial demand in their history.
"The organic demand for AI and the data centers that support it is so strong that the buildout will continue without missing a beat," said Shumate. "The key is for local governments to meet the moment and protect their communities without missing out on the economic benefits provided by such projects."
What happens to the surface transportation bill?
Fisher laid out the immediate deadline: Congress must decide on the surface transportation bill by Dec. 11, whether through a short-term extension or passage of the BUILD America 250 Act. With the massive Democrat electoral victory, however, he said it now seems unlikely lawmakers will pass a surface transportation bill this year. Winning representatives and senators will be sworn in in January, so current members will likely wait until then to discuss the bill.
"Democrats will be content with extending the current law so they can draft a bill more to their liking," said Fisher. "I do think Democrats will prioritize a surface transportation bill next Congress."
Swearingen agreed the current law is "likely to be extended with full government funding into 2027." That extension, however, does not ultimately provide a stable planning horizon for contractors, said Fisher.
"The failure to enact a long-term surface reauthorization bill means a lack of clarity on the future of federal funding for infrastructure projects across the country," said Fisher. "State departments of transportation don't have the certainty to begin major projects and contractors won't be confident of future work."
The stakes are measurable. The Infrastructure Investment and Jobs Act raised average annual federal highway funding by about 62% and public transit funding by about 67% in nominal terms compared with the preceding authorization, said Guckes.
"With current authorizations nearing expiration, Congress will have to decide whether to maintain, increase or restructure those commitments," said Guckes. "History suggests that regardless of party control funding will likely be maintained or increased."
For contractors, the practical read is this: data center work continues but with longer permitting timelines in states like Texas and Michigan, while highway and transit funding likely arrives through an extension rather than a new multiyear authorization — at least until the next Congress takes up the bill in January.
Source: Construction Dive
More from Marcus Bennett
Show full bio
Correspondent covering money, funding and market shifts around construction industry, architecture, interior design at Built Current.
229 articles