CoA Flags P3.328 Billion in Failed TIEZA Tourism Projects
CoA says TIEZA failed to implement P3.328 billion in tourism projects, citing poor planning, idle P80.43-million hyperbaric units and P216.9 million in unsettled charges.
- Section
- Construction
- Author
- By Priya Raman
- Filed
- Length
- 3 min read
Key takeaways
- CoA found TIEZA failed to effectively implement P3.328 billion in locally funded tourism projects.
- Hyperbaric chamber units costing P80.430 million posted net losses of P10.305 million in 2025; only one of five units works.
- TIEZA has P216.916 million in unsettled audit suspensions and charges as of Dec. 31, 2025.
- 58 of 115 prior audit recommendations remain unimplemented.
- CoA still issued an unqualified opinion on TIEZA's 2025 and 2024 financial statements.
The Philippines' Commission on Audit (CoA) has found that TIEZA, the Tourism Infrastructure and Enterprise Zone Authority, failed to effectively implement P3.328 billion worth of locally funded tourism infrastructure projects. The cause, auditors said, was inadequate planning, engineering, supervision and monitoring.
The finding appears in CoA's 2025 annual audit report on the agency. State auditors documented delays and non-implementation across several infrastructure projects. They raised concerns over TIEZA's project management and its use of public funds.
"The TIEZA was not able to effectively implement a significant number of locally-funded projects with an aggregate contract cost of P3.328 billion due to inadequate planning, detailed engineering, supervision, and monitoring," CoA said in the report.
What does the audit actually flag?
The problems run well beyond delayed construction. CoA also found that TIEZA failed to properly account for two of its flagship convention centers:
- The Iloilo Convention Center, valued at P529.474 million.
- The Aquilino Q. Pimentel Jr. International Convention Center, worth P1.114 billion.
Both buildings were booked as single asset items under the Other Structures account. Auditors said the agency did not identify or classify their individual components, a practice contrary to the International Public Sector Accounting Standards (the global accounting rules for government entities).
Untitled land and idle equipment
TIEZA also sits on valuable property it does not legally hold in its own name. Auditors found 19 parcels of land at the agency's head office, worth P112.906 million, still untitled. Another 13 properties at the Zamboanga Golf Course and Beach Park, valued at P18.922 million, face the same problem.
The agency's hyperbaric chamber system (pressurized medical units used to treat diving-related conditions) is losing money. Five units procured in 2013 and 2019 cost a combined P80.430 million. They generated net operating losses of P10.305 million in 2025 and P9.552 million in 2024.
Only one of the five units is operational. The rest sit unused. Auditors questioned the program's economic viability and sustainability. Meanwhile, housing facilities for four additional HCS units procured in 2024 for P339.795 million have yet to be constructed.
Duplicated booths and delayed furniture
Procurement decisions drew scrutiny too. CoA questioned the establishment of seven Tourist First Aid Booths, finding their objectives and intended beneficiaries substantially overlapped with seven existing Tourist First Aid Stations.
The auditors also flagged P82.899 million worth of furniture for the Banaue Hotel and Youth Hostel. The furniture was ordered while structural renovations were ongoing or suspended. Those circumstances contributed to a 288-day delay in the project.
Sponsorship spending raised another red flag. CoA cited P26.348 million in sponsorship expenditures, including support for the LIV Golf tournament, because the agency has no established spending limits for such outlays.
What does this change for TIEZA?
The agency carries significant unresolved audit baggage. As of Dec. 31, 2025, TIEZA had P216.916 million in unsettled audit suspensions, disallowances and charges (mechanisms by which the state freezes or claws back questioned spending). It has also failed to implement 58 of 115 audit recommendations from previous years.
Yet the financial picture is not a total rebuke. Despite the operational and accounting deficiencies, CoA issued an unqualified opinion — the cleanest audit verdict — on the fair presentation of TIEZA's financial statements for 2025 and 2024.
The unmet backlog of 58 recommendations and the mounting hyperbaric losses suggest the pressure now shifts to whether TIEZA can convert the audit's findings into corrective action before its next annual review.
Source: bworldonline.com